Rehandle groups (rehandle movements)

Rehandle groups allow you to model the physical rehandle of material from a stockpile to another location using actual resources like loaders or conveyors. While the Product Optimiser (PO) determines optimal flows based on blending and quality targets, these flows are virtual by default. Rehandle groups bridge this gap by linking physical resources to specific material movements, providing accurate planning and reporting.

What are rehandle groups?

A rehandle group represents a set of material movements (arcs) between a stockpile and another intermediate or a final location (e.g., stockpile → crusher). These groups are defined in the material flow diagram and are used to associate physical resources with specific rehandling tasks.

Assign resources to rehandle groups

A resource can perform rehandling on a rehandle group’s movements. To set this up, allocate the resource to the Rehandle Operations activity. This activity is system-defined and configured in System Config > Resources.

Each rehandle resource has time usage fields (refer to Client > Resources) that define how much of the resource’s available operating time can be allocated to each rehandle group per period.

Rehandle contribution

Each resource’s contribution to a rehandle group is based on:

These values determine how much material the resource can move in a given period.

Example scenario

Rehandle groups

A site has the following rehandle groups:

Group

Movements

Group1

HGSx Stockpile → Crusher

HGOx Stockpile → Crusher

Group2

LGSX Stockpile → Crusher

Resources

The site has the following resources:

Source

Activities

Rate (t/h)

Shift/Period Length

Total Delays

Operating Time

Resource1

Rehandle Operations

800 t/h

12 hours

30 mins

11.5 hours

Resource2

Rehandle Operations

800 t/h

12 hours

30 mins

11.5 hours

Resource allocation per period

The resources have the following rehandle allocation percentages (defined in Client > Resources). These allocations are the same across each period.

Resource

Rehandle Group

% Time

Max Time

Max Moved (t)

Resource1

Group1

60%

6h 54m

5,520

Group2

40%

4h 36m

3,680

Resource2

Group1

100%

11h 30m

9,200

Group2

0%

0h 0m

0

For each resource:

Stockpile inventories at start of period

The stockpile inventories at the start of Period 10 are shown below.

Stockpile

Inventory (t)

Rehandle Group

HGSx Stockpile

20,000

Group 1

HGOx Stockpile

16,000

Group 1

LGSx Stockpile

18,000

Group 2

Scheduling logic

To allocate resources, the schedule respects the resource limits (refer to Resource allocation per period above) per group:

Example allocation

The Product Optimiser attempts to get only one resource to mine from a given stockpile at a time. Before another resource can mine from a stockpile, the other resource must exhaust its capacity on the stockpile within the period. This isn’t always possible – but it’s the likely allocation scenario.

A possible allocation plan for rehandling in Period 10, based on the logic and constraints, is shown below.

  1. Resource2 rehandles all tonnes from Group1’s contribution to HGSx (8,179 t).

  2. Resource2 then rehandles some of Group1’s contribution to HGOx (1,021 t).

    • The resource’s periodic capacity (800 t/h × 12hrs = 9,600 t capacity) prevents the resource from rehandling more of HGOx.

  1. Resource1 then mines as much as it can from HGOx, following its Group1 contribution (5,520 t)

  2. Resource1 then mines as much as it can from LGSx, following its Group2 contribution (3,680 t).

#

Resource

Group

Stockpile

Tonnes Moved

Resource capacity

1

Resource2

Group1

HGSx

8,179

9200 t

2

Resource2

Group1

HGOx

1,021

3

Resource1

Group1

HGOx

5,520

9,200 t

4

Resource1

Group2

LGSx

3,680

The list of rehandling tasks performed within this scenario in Period10

Stockpile

Original Inventory

Tonnes Moved

New Inventory

HGSx

20,000

8,179

11,821

HGOx

16,000

6,541

9,459

LGSx

18,000

3,680

14,320

The stockpile inventories and movements in Period10

The distribution of resources across stockpiles within a group may vary depending on scheduling logic. This example shows one valid allocation that meets all constraints.

Rehandle production rate

The production rate of a rehandle resource is set in System Config > Resources.

Rehandle capacity (unlimited or limited)

Each rehandle group can have an unlimited or limited capacity.

Limited capacity

When enabled, the schedule applies a constraint to each rehandle group that limits how much material can be moved across its movements (arcs) in each period. This limit is calculated based on the combined capabilities of the resources assigned to the group.

For each resource, the system considers:

These values are used to calculate how much material each resource can contribute to the group in a given period. The total group capacity is the sum of these contributions. The schedule ensures that the total material moved within the group doesn’t exceed this calculated limit.

Unlimited capacity

No constraints are applied, allowing unrestricted movement across the group’s arcs during scheduling.

If the material moved across the rehandle group exceeds the amount that the resources can handle, the schedule increases the resources’ production rates to accommodate all the material. A schedule warning flags this.

Rehandle group processing logic

Rehandle group limitations

Gantt chart visualisation

Rehandle resources are displayed on the Gantt chart (see Build schedule using Gantt Chart (Gantt tab)) like any other resource. When these resources perform rehandling tasks, a Rehandle Operation bar is shown to indicate the activity. These rehandling delays are non-adjustable directly on the chart.

You can assign in-pit activities to rehandle resources, provided those resources are permitted to perform such tasks.

Reporting Gantt chart

You can build custom reports (refer to Create pivot tables and charts (Reporting tab)) and Gantt charts (refer to Gantt Reporting tab (Gantt Report tab)) to see the full detail of each material movement assigned to a rehandle group, such as the:

Visualise multiple operations

Custom Gantt charts can integrate rehandle tasks with other operational schedules, such as in-pit mining, plant maintenance, and train logistics. This unified view helps identify dependencies and optimise coordination across different activities.

For example, a custom Gantt chart could display:

For staged stockpiles, the report can display detailed build sequences, including stacking and reclaiming start and finish times. These tasks provide a complete picture of stockpile activity alongside rehandling operations.